Blog post category: Public School Work

Lodi Central Kitchen Equipped for Efficiency

Most of the equipment is installed in Lodi Unified School District’s new central kitchen, which will be operational by July 28. As the project wraps up, Lodi USD accomplishes a 10-year dream … more

Steady Progress on Lodi Central School Kitchen

The central kitchen project for Lodi Unified School District is moving along as the floor is finished and water pipe, electric conduit, and HVAC ducts are installed in the structural grid overhead. … more

Central Kitchen To Boost Fresh School Lunches

Just a quick update on our Central School Kitchen project in Lodi where a former warehouse is being transformed into a modern school kitchen. Currently, insulation is going in and equipment such as … more

Sparks Fly as Central Kitchen Progresses

Sparks fly as a carpenter cuts steel framing last week at Lodi Unified School District’s Central Kitchen project. Metal framing is now complete as the former warehouse is transformed into a modern kitchen … more

Central School Kitchen Project Advances

Construction on a 16,000+ square-foot former warehouse is moving swiftly, and Lodi Unified School District Central Kitchen is taking shape. The new steel frame is constructed to carry the load of updated … more

Central Kitchen Underway for Lodi USD

A 16,000+ square-foot former warehouse is being transformed into an efficient central kitchen for Lodi Unified School District. The kitchen will streamline the provision of more than 3,000 meals a day to … more

New Central Kitchen for Lodi Unified School District

Henry + Associates Architects is proud to be part of the team working on the new central kitchen for Lodi USD. The kitchen will allow the district to provide 3,000+ meals per … more

New School Kitchens Almost Ready

The kitchen renovations at Lakewood Elementary and Morada Middle School in Lodi are nearing completion. Installment of food service equipment is underway, and new ventilation hoods are in place. Water, sewer and … more

Construction at Lakewood and Morada School Kitchens

Construction is on track at Lakewood Elementary and Morada Middle Schools as we work to complete the kitchen remodels at both sites by the end of September. The kitchens will be all … more

Lakewood and Morada School Kitchens

Construction is happening at Lakewood Elementary and Morada Middle Schools in Lodi, and the 40 year-old kitchens at both sites are stripped down and being transformed into commercial-grade workspaces with stainless steel … more

School Kitchen Remodels: Before and After

What a difference four months and some well-planned renovation work make. Here are a few before and after photos of the kitchen remodels at Davis and Heritage Elementary Schools in Lodi.  Both kitchens were stripped … more

New Kitchen at Davis Elementary

Here are a few photos of the completed kitchen remodel at Davis Elementary School in Lodi. The transformation is dramatic with a centalized counter, increased open space, and a design that makes the … more

Maximazing Space in School Kitchens

The kitchen remodels at Davis and Heritage elementary schools in Lodi are under construction with both kitchens stripped down to the studs. The kitchens are getting new electrical and plumbing systems, and the spaces … more

School Kitchen Renovations Begin

Henry + Associates Architects are happy to be working with Lodi Unified School District to renovate the kitchens at Davis and Heritage Elementary Schools. Here are a few “before” photos of the … more